Seismic retrofitting as part of construction on Lot F will continue to keep sections of the parking lot closed off until the middle of next year.
Construction is being done in sections to reduce the impact on student parking, according to Director of Facilities, Tom Brown.
The middle section is currently under construction on both levels, and blocks thru traffic on the second level.
“That project will not be completed until 2017,” Brown said. “We’re doing it in three sections.”
The contractor, AMG associates, is also installing a fire sprinkler system in the ground level of the lot and will be resurfacing the upper level roadway, according to Brown.
The projected completion date is scheduled for May 2017.